Subpart 3Procedure for making and responding to payment claims

19 Interpretation
  • In this subpart, unless the context otherwise requires,—

    claimed amount means an amount of progress payment specified in a payment claim that the payee claims to be due for construction work carried out

    payee means the party to a construction contract who is entitled to a progress payment

    payer means the party to a construction contract who is liable for that payment

    scheduled amount means an amount of progress payment specified in a payment schedule that the payer proposes to pay to the payee in response to a payment claim.