(1) This section applies if—
(a) a claimant has referred to adjudication a dispute about whether an amount is payable by a respondent under the construction contract; and
(b) the claimant has sought, in the notice of adjudication, the adjudicator's approval for the issue of a charging order in respect of a construction site owned by the respondent; and
(c) the adjudicator has determined that the respondent—
(i) is liable to pay (whether in whole or in part) the amount claimed in the adjudication; and
(ii) is the owner of the construction site.
(2) If this section applies, the adjudicator must—
(a) approve the issue of a charging order in respect of the construction site owned by the respondent; and
(b) record that approval in his or her determination accordingly; and
(c) include in his or her determination sufficient particulars to identify the construction site to which the approval for the issue of a charging order relates.