97 How to apply for certificate of acceptance
  • An application for a certificate of acceptance must—

    • (a) be in the prescribed form; and

    • (b) if available, be accompanied by plans and specifications that are—

      • (i) required by regulations made under section 402; or

      • (ii) if the regulations do not so require, required by the territorial authority; and

    • (c) contain or be accompanied by any other information that the territorial authority reasonably requires; and

    • (d) be accompanied by the charge fixed by the territorial authority; and

    • (e) in the case of an application under section 96(1)(a), be accompanied by any fees, charges, or levies that would have been payable had the owner, or the owner's predecessor in title, applied for a building consent before carrying out the building work; and

    • (f) if a project information memorandum for the building work has been issued under section 34, be accompanied by the project information memorandum; and

    • (g) if a compliance schedule is required as a result of the building work, have attached to it a list of all specified systems for the building; or

    • (h) if an amendment to an existing compliance schedule is required as a result of the building work, have attached to it a list of all specified systems that are being—

      • (i) altered in the course of the building work:

      • (ii) added to the building in the course of the building work:

      • (iii) removed from the building in the course of the building work.