“(1) If the Agency receives a request in accordance with subsection (2), the Agency must respond, in writing, within 30 working days of receiving it.
“(2) The requests to which subsection (1) applies are those from local authorities, or owners of any pipe, line, or other works associated with wastewater or the supply of water, electricity, gas, or telecommunications, for access to a motorway for the purpose of constructing, maintaining, or in any other way altering any such pipe, line, or other works, or any wire, cable, pipe, tower, pole, or other structure or thing on, over, or under the motorway.”