(1) As soon as practicable following receipt of a proposed critical contingency management plan under regulation 24 or a proposed amendment under regulation 33(4)(c), 34(6)(c), or 65(3)(c), the industry body must provide the proposed plan or proposed amendment to the expert adviser and the critical contingency operator.
(2) In reviewing the proposed critical contingency management plan or proposed amendment under regulation 29, the expert adviser must consult with the critical contingency operator.
(3) The critical contingency operator may provide the expert adviser with a report on the proposed critical contingency management plan or proposed amendment in relation to any issues it perceives as material to the review by the expert adviser under regulation 29.
(4) Any report prepared by the critical contingency operator under subclause (3) must be submitted to the expert adviser no later than 10 business days after the proposed critical contingency management plan or proposed amendment was received from the industry body.