Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
Checking for alerts... Loading...
Version as at 8 October 2026

Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
(SR 2009/397)
Regulations name: amended, on 8 October 2026, by regulation 4 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Anand Satyanand, Governor-General
Order in Council
At Wellington this 14th day of December 2009
Present:
His Excellency the Governor-General in Council
Note
The Parliamentary Counsel Office has made editorial and format changes to this version using the powers under subpart 2 of Part 3 of the Legislation Act 2019.
Note 4 at the end of this version provides a list of the amendments included in it.
These regulations are administered by the Ministry for Cities, Environment, Regions, and Transport.
Pursuant to section 43 of the Resource Management Act 1991, His Excellency the Governor-General, acting on the advice and with the consent of the Executive Council, and on the recommendation of the Minister for the Environment given in accordance with section 44 of that Act, makes the following regulations.
Contents
Regulations
1 Title
These regulations are the Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009.
Regulation 1: amended, on 8 October 2026, by regulation 4 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
2 Commencement
These regulations come into force on 14 January 2010.
Part 1 Preliminary provisions
Part 1 heading: inserted, on 8 October 2026, by regulation 5 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
3 Interpretation
(1)
In these regulations, unless the context requires another meaning,—
abrasive blasting means cleaning, smoothing, roughening, cutting, or removing part of the surface of any article by using, as an abrasive, a jet of sand, metal, shot, grit, or other material propelled by a blast of compressed air or steam or water or by a wheel
Act means the Resource Management Act 1991
ancillary electricity network activities means all supporting and subsidiary activities needed to provide for the operation, maintenance, and upgrading of the electricity network, including, but not limited to,—
(a)
clearing vegetation; and
(b)
tree trimming; and
(c)
earthworks; and
(d)
maintaining and upgrading access tracks and accessways; and
(e)
providing telecommunications
ancillary equipment on support structures—
(a)
includes the following equipment mounted on a support structure:
(i)
transformer boxes:
(ii)
fuses:
(iii)
circuit breakers:
(iv)
switchgear:
(v)
voltage regulators:
(vi)
pole-mounted batteries:
(vii)
isolators:
(viii)
junction boxes:
(ix)
lightning arrestors:
(x)
surge protectors:
(xi)
equipment that is associated with any equipment listed in subparagraphs (i) to (x); but
(b)
does not include telecommunication devices or hardware associated with a support structure (such as guy-wires, cross-arms, and insulators)
blasting means—
(a)
abrasive blasting; and
(b)
water blasting
cabinet means casing or a structure that is fixed to the ground and contains equipment that is necessary to operate part of the electricity distribution network
circuit means conductors on a transmission line or distribution line that together form a single electrical connection between 2 or more system nodes
conductor—
(a)
means wire or cable used for carrying electric current along a transmission line or distribution line; and
(b)
includes any hardware and insulation associated with the wire or cable
distribution line—
(a)
means the facilities and structures used for, or associated with, the overhead or underground distribution of electricity; and
(b)
includes cables, wires, conductors, support structures, ancillary equipment on support structures, telecommunication cables, and telecommunication devices to which paragraph (a) applies; but
(c)
does not include electricity substations
dry abrasive blasting means abrasive blasting using materials to which no water has been added
earth-wire—
(a)
means a protective wire that provides a path to ground for electrical current from a fault or lightning strike; and
(b)
includes an earth-wire that contains optic fibres; and
(c)
includes any hardware associated with the wire
earthworks—
(a)
means the alteration or disturbance of land, including by moving, removing, placing, blading, cutting, contouring, filling, or excavating earth (or any matter constituting the land, including soil, clay, sand, and rock); but
(b)
does not include gardening, cultivation, and disturbance of land for the installation of fence posts
electric vehicle charging infrastructure means all buildings, structures, equipment, and other facilities associated with the charging of electric vehicles,—
(a)
including electric vehicle charging car parks and manoeuvring spaces, chargers, cabinets, batteries, bollards, and wheel stops; but
(b)
not including lighting, signage, and retail sales of any other goods or services
electricity distribution network means—
(a)
all assets that provide electricity distribution and that—
(i)
are owned or used by a person or body who is both an electricity distributor and an electricity operator; and
(ii)
comprise the network of distribution lines, switching stations, transformers, kiosks, cabinets, connections to grid exit points, customer connections, and works used to distribute electricity from the electricity transmission network or generation activities; and
(b)
ancillary electricity network activities
electricity network means the electricity transmission network and the electricity distribution network
electricity transmission network means—
(a)
all assets that provide electricity transmission and that—
(i)
are owned or used by Transpower New Zealand Limited; and
(ii)
comprise all parts of the national grid of transmission lines and cables (overhead, underground, and submarine, including the inter-island high-voltage direct current link), stations, and other works used to connect grid injection points and grid exit points to convey electricity; and
(b)
ancillary electricity network activities
environmental management plan means an environmental management plan that meets the requirements of regulation 25A
existing cabinet means a cabinet—
(a)
that was operational, or was able to be operated, as at 8 October 2026; and
(b)
described in paragraph (a) that is altered or relocated in accordance with these regulations; and
(c)
that, in accordance with these regulations, replaces a cabinet described in paragraph (a)
existing distribution line means a distribution line—
(a)
that was operational, or was able to be operated, as at 8 October 2026; and
(b)
described in paragraph (a) that is altered or relocated in accordance with these regulations; and
(c)
that, in accordance with these regulations, replaces a distribution line described in paragraph (a)
existing distribution line support structure means a distribution line support structure—
(a)
that was operational, or was able to be operated, as at 8 October 2026; and
(b)
described in paragraph (a) that is altered or relocated in accordance with these regulations; and
(c)
that, in accordance with these regulations, replaces a distribution line support structure described in paragraph (a)
existing transmission line—
(a)
means a transmission line that was operational, or was able to be operated, as at 14 January 2010; and
(b)
includes a transmission line described in paragraph (a) that is altered or relocated in accordance with these regulations; and
(c)
includes a transmission line that, in accordance with these regulations, replaces a transmission line described in paragraph (a)
footprint means the outline of the land occupied by a tower or cabinet, formed by drawing straight lines between the outermost edges of the outermost parts of the tower or cabinet at ground level
guy-wire means a cable or wire designed to add stability to a structure (including any associated pole or anchor block)
height means,—
(a)
in relation to a support structure or cabinet, the vertical distance between the ground level at the centre of the support structure or cabinet, and the highest point of the support structure or cabinet including conductors but excluding insulators; and
(b)
in relation to a telecommunication device, the vertical distance between the highest part of the support structure and the highest part of the telecommunication device; and
(c)
in any other case, the vertical distance between ground level and the highest part of any feature, structure, or building above that point
historic heritage place or area means any historic heritage site, items, building or area protected by a rule in a plan because of its historic heritage value, and includes a site of significance to Māori
industrial zone means an industrial zone listed and described in standard 8 (zone framework standard) of the National Planning Standards or an equivalent zone
LAeq has the same meaning as “time-average A-weighted sound pressure level”
in NZS 6801:2008 Acoustics—Measurement of environmental sound
LAFmax has the same meaning as “maximum A-frequency weighted, F-time weighted sound pressure level”
in NZS 6801:2008 Acoustics—Measurement of environmental sound
land includes—
(a)
land covered by water and the air space above land; and
(b)
the bed of a lake or river; and
(c)
the surface of water in a lake or river
Māori purpose zone has the same meaning as in standard 8 (zone framework standard) of the National Planning Standards or an equivalent zone
modelled conductor noise level means the noise level generated by the transmission line and conductor configuration, taking into account new wet conductor characteristics, but without—
(a)
considering the presence of any buildings; and
(b)
any adjustments for special audible characteristics (as that term is defined in NZS 6802:2008 Acoustics—Environmental noise)
national grid subdivision corridor has the meaning given in regulation 73(1)
national grid yard has the meaning given in regulation 73(2)
National Planning Standards means the National Planning Standards whose approval under section 58E of the Act was notified on 5 April 2019 (as amended or replaced from time to time)
natural area means an area that is protected by a rule because it has outstanding natural features or landscapes, significant indigenous vegetation, or significant habitats of indigenous fauna
NZECP 34:2001 means the New Zealand Electrical Code of Practice for Electrical Safe Distances 2001 (NZECP 34:2001)
occupied building means a building that is, or is intended to be, regularly occupied by 1 or more people
operation, in relation to the use of a transmission line or distribution line, means to convey electricity
overland flow path means the path that water takes over land if there is flooding
pole—
(a)
means a structure made of wood, reinforced concrete, steel, or other material that supports conductors as part of a transmission line or distribution line and that—
(i)
has no more than 3 vertical supports, not including a pole that forms part of a guy-wire; and
(ii)
is not a steel-lattice structure; and
(b)
includes the hardware associated with the structure (such as insulators, cross-arms, and guy-wires) and the structure’s foundations
road reserve means a road and any land next to it up to the legal boundary of the adjoining land
rural zone means a rural zone, including a settlement zone, listed and described in standard 8 (zone framework standard) of the National Planning Standards or an equivalent zone
sensitive activity means any of the following:
(a)
residential activity, including activity in visitor accommodation or retirement accommodation:
(b)
educational activity:
(c)
health care activity:
(d)
congregation within any place of worship:
(e)
activity at custodial or supervised accommodation where residents are detained on site:
(f)
activity at a marae or papakāinga
simplex configuration means a configuration of a transmission line in which each of the 3 wires that make up a circuit consists of a single conductor
site-specific management plan means a site-specific management plan that meets the requirements of regulation 25B
special purpose zone means—
(a)
a special purpose zone listed and described in standard 8 (zone framework standard) of the National Planning Standards or an equivalent zone; or
(b)
an additional special purpose zone created in accordance with standard 8 (zone framework standard) of the National Planning Standards or an equivalent zone
support structure means a tower or pole
telecommunication cable—
(a)
means a wire or cable used for telecommunication; and
(b)
includes any hardware associated with the wire or cable
telecommunication device—
(a)
means a device (for example, an antenna) that—
(i)
facilitates the operation of a transmission line or distribution line; and
(ii)
receives or transmits telecommunication signals; and
(b)
includes any hardware associated with the device; but
(c)
does not include a telecommunication cable
temporary line deviation means the construction and use of a temporary section of transmission line or distribution line
temporary structure means a non-permanent structure, and any associated lighting, erected only for a specific maintenance or upgrading task
termination structure means a support structure or gantry used for the transition between an overhead and an underground transmission line or distribution line
tower—
(a)
means a steel-lattice structure that supports conductors as part of a transmission line or distribution line; and
(b)
includes the hardware associated with the structure (such as insulators, cross-arms, and guy-wires) and the structure’s foundations
transmission line—
(a)
means the facilities and structures used for, or associated with, the overhead or underground transmission of electricity in the electricity transmission network, including the transition from overhead to underground transmission; and
(b)
includes wires, conductors, support structures, ancillary equipment on support structures, telecommunication cables, and telecommunication devices to which paragraph (a) applies; but
(c)
does not include an electricity substation
transport corridor has the meaning set out in section 4 of the Utilities Access Act 2010
undergrounding—
(a)
means replacing overhead transmission lines with underground transmission lines or overhead distribution lines with underground distribution lines; and
(b)
includes altering, relocating, or replacing a tower or pole at 1 or both ends of an underground transmission line or underground distribution line so that the tower or pole becomes a termination structure
upgrading means improving the capacity, level of service, efficiency, safety, security, resilience, effectiveness, or longevity of the existing physical components of the electricity network, and includes replacing, renewing, adding, expanding, and intensifying those components
water blasting means directing water at pressure to clean or wash a structure’s surface
wet abrasive blasting means abrasive blasting using material to which water has been added, and includes air-assisted wet abrasive blasting.
(2)
[Revoked](3)
Unless the context requires another meaning, a term or expression that is defined in the Act and used, but not defined, in these regulations has the meaning given by the Act.
Regulation 3(1) abrasive blasting: replaced, on 8 October 2026, by regulation 6(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) ancillary electricity network activities: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) ancillary equipment on support structures: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) base footprint: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) base height: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) base position: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) base width: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) blasting: replaced, on 8 October 2026, by regulation 6(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) cabinet: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) circuit: amended, on 8 October 2026, by regulation 6(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) conductor paragraph (a): amended, on 8 October 2026, by regulation 6(6) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) distribution line: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) dry abrasive blasting: replaced, on 8 October 2026, by regulation 6(7) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) earthworks: replaced, on 8 October 2026, by regulation 6(8) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) electric vehicle charging infrastructure: inserted, on 7 May 2026, by regulation 5(1) of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3(1) electricity distribution network: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) electricity network: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) electricity transmission network: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) envelope for controlled activities: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) envelope for permitted activities: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) environmental management plan: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) existing cabinet: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) existing distribution line: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) existing distribution line support structure: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) existing transmission line paragraph (a): amended, on 8 October 2026, by regulation 6(9) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) footprint: amended, on 8 October 2026, by regulation 6(10) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) guy-wire: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) height: replaced, on 8 October 2026, by regulation 6(11) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) historic heritage area: revoked, on 8 October 2026, by regulation 6(12) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) historic heritage place or area: inserted, on 8 October 2026, by regulation 6(12) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) industrial zone: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) LAeq: inserted, on 7 May 2026, by regulation 5(1) of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3(1) LAFmax: inserted, on 7 May 2026, by regulation 5(1) of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3(1) Māori purpose zone: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) modelled conductor noise level: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) national grid: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) national grid subdivision corridor: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) national grid yard: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) National Planning Standards: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) normal operating conditions: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) NZECP 34:2001: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) operation: replaced, on 7 May 2026, by regulation 5(2) of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3(1) operation: amended, on 8 October 2026, by regulation 6(13) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) pole: replaced, on 8 October 2026, by regulation 6(14) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) road reserve: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) rural zone: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) sensitive activity: inserted, on 8 October 2026, by regulation 6(15) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) sensitive land use: revoked, on 8 October 2026, by regulation 6(15) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) simplex configuration: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) site-specific management plan: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) special purpose zone: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) support structure: inserted, on 8 October 2026, by regulation 6(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) telecommunication device paragraph (a)(i): amended, on 8 October 2026, by regulation 6(16) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) temporary line deviation: replaced, on 8 October 2026, by regulation 6(17) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) temporary structure: replaced, on 8 October 2026, by regulation 6(18) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) termination structure: replaced, on 8 October 2026, by regulation 6(19) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) tower paragraph (a): amended, on 8 October 2026, by regulation 6(20) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) transmission line paragraph (a): amended, on 8 October 2026, by regulation 6(21)(a) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) transmission line paragraph (b): amended, on 8 October 2026, by regulation 6(21)(b) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) transmission line support structure: revoked, on 8 October 2026, by regulation 6(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) transport corridor: inserted, on 7 May 2026, by regulation 5(1) of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3(1) undergrounding paragraph (a): amended, on 8 October 2026, by regulation 6(22)(a) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) undergrounding paragraph (b): amended, on 8 October 2026, by regulation 6(22)(b) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) upgrading: replaced, on 8 October 2026, by regulation 6(23) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(1) wet abrasive blasting: replaced, on 8 October 2026, by regulation 6(24) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3(2): revoked, on 8 October 2026, by regulation 6(25) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
3AA Transitional, savings, and related provisions
The transitional, savings, and related provisions set out in Schedule 1 have effect according to their terms.
Regulation 3AA: inserted, on 8 October 2026, by regulation 7 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
3A Noise
(1)
In these regulations, unless otherwise stated, noise must be measured in accordance with NZS 6801:2008 Acoustics—Measurement of environmental sound and assessed in accordance with NZS 6802:2008 Acoustics—Environmental noise.
(2)
In regulation 54, noise must be—
(a)
adjusted in accordance with NZS 6801:2008 Acoustics—Measurement of environmental sound to a free field incident sound level; and
(b)
measured at a point that is 1 metre from a building containing a sensitive activity (if applicable).
Regulation 3A: inserted, on 7 May 2026, by regulation 6 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 3A(1): amended, on 8 October 2026, by regulation 8(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 3A(2): inserted, on 8 October 2026, by regulation 8(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
4 Application of regulations
(1AAA)
Subparts 1 and 3 of Part 2 apply only to activities in relation to existing transmission lines.
(1AAB)
Subpart 2 of Part 2 applies to activities in relation to distribution lines and existing transmission lines.
(1)
The activities specified in subparts 1 to 3 of Part 2 that relate to existing transmission lines include the following activities (if applicable):
(a)
a construction activity:
(b)
a use of land or occupation of the coastal marine area in relation to an existing transmission line (within the meanings of use and occupy given by section 2(1) of the Act):
(c)
maintaining, using, upgrading, or removing an access track to an existing transmission line:
(d)
undergrounding an existing transmission line.
(1A)
The activities specified in subparts 2 and 5 of Part 2 that relate to distribution lines include the following activities (if applicable):
(a)
a construction activity:
(b)
a use of land (within the meaning of use given by section 2(1) of the Act):
(c)
occupation of the coastal marine area in relation to an existing distribution line (within the meaning of occupy given by section 2(1) of the Act):
(d)
maintaining, using, upgrading, or removing an access track to an existing distribution line:
(e)
undergrounding a distribution line.
(2)
However, subparts 1 to 5 of Part 2 do not apply to—
(a)
the construction or use of a bridge or culvert to access an existing transmission line or distribution line; or
(b)
the control of the use of land for the purpose of the prevention or mitigation of any adverse effects of the storage, use, disposal, or transportation of hazardous substances; or
(c)
the refuelling of a vehicle or equipment; or
(d)
the use of land as a landing area for helicopters; or
(e)
an activity carried out in relation to an electricity substation.
(f)
[Revoked](3)
Subpart 6 of Part 2 does not apply to an activity or works—
(a)
undertaken by Transpower New Zealand Limited or persons acting under the direction of Transpower New Zealand Limited; or
(b)
in an area that is covered by the Auckland Unitary Plan.
(4)
Subpart 7 of Part 2 does not apply to electricity distribution businesses or persons acting under the direction of an electricity distribution business.
Regulation 4 heading: replaced, on 8 October 2026, by regulation 9(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1AAA): inserted, on 8 October 2026, by regulation 9(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1AAB): inserted, on 8 October 2026, by regulation 9(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1): amended, on 8 October 2026, by regulation 9(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1): amended, on 7 May 2026, by regulation 7 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 4(1)(b): amended, on 8 October 2026, by regulation 9(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1)(c): amended, on 8 October 2026, by regulation 9(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(1A): inserted, on 8 October 2026, by regulation 9(6) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(2): amended, on 8 October 2026, by regulation 9(7) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(2)(a): amended, on 8 October 2026, by regulation 9(8) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(2)(f): revoked, on 8 October 2026, by regulation 9(9) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(3): inserted, on 8 October 2026, by regulation 9(10) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 4(4): inserted, on 8 October 2026, by regulation 9(10) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
4A Functions of regional councils and territorial authorities
The functions of regional councils and territorial authorities under sections 30 and 31 of the Act, in relation to these regulations, are as specified in the following table:
| Provision | Local authority with functions in relation to activity concerned | |
|---|---|---|
| Regulations 5 to 24, 27, 35 to 44, and 46 to 92 | Territorial authority | |
| Regulations 25, 26, 28 to 34, and 36 | Regional council and territorial authority |
Regulation 4A: inserted, on 8 October 2026, by regulation 10 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Part 2 Regulation of electricity network activities
Part 2 heading: inserted, on 8 October 2026, by regulation 10 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 1—Electricity transmission
Subpart 1 heading: inserted, on 8 October 2026, by regulation 10 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Operation of transmission line, use of access track, or occupation of land
Heading: amended, on 8 October 2026, by regulation 11 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
5 Permitted activities
(1)
The operation of an existing transmission line is a permitted activity.
(2)
The use of an access track to an existing transmission line is a permitted activity.
(3)
The occupation of land for an existing transmission line is a permitted activity.
Regulation 5(3): inserted, on 8 October 2026, by regulation 12 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Overhead conductors, earth-wires, overhead telecommunication cables, optical ground wires, and adding overhead circuits
Heading: amended, on 8 October 2026, by regulation 13 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
6 Permitted activities: overhead conductors
(1)
Adding an overhead conductor, or part of an overhead conductor, to an existing transmission line (except as part of adding an overhead circuit) is a permitted activity if—
(a)
both of the conditions in subclauses (5) and (7) are complied with; and
(b)
all of the applicable conditions in regulation 10(2) to (8) are complied with.
(2)
Replacing an overhead conductor, or part of an overhead conductor, on an existing transmission line is a permitted activity if both of the conditions in subclauses (6) and (7) are complied with.
(3)
Maintaining an overhead conductor on an existing transmission line is a permitted activity.
Conditions
(4)
[Revoked](5)
The diameter of a new conductor, or a new part of a conductor, must not exceed 50 millimetres.
(6)
The diameter of a replacement conductor, or a replacement part of a conductor, must not exceed—
(a)
the diameter of the existing conductor or part; or
(b)
50 millimetres, if the diameter of the existing conductor or part is less than 50 millimetres.
(7)
A new conductor, or part of a new conductor, on an existing transmission line operating at 220 kV in a simplex configuration must comply with regulation 10A.
Regulation 6(1)(a): amended, on 8 October 2026, by regulation 14(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 6(2): amended, on 8 October 2026, by regulation 14(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 6(4): revoked, on 8 October 2026, by regulation 14(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 6(5): amended, on 8 October 2026, by regulation 14(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 6(6)(b): amended, on 8 October 2026, by regulation 14(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 6(7): inserted, on 8 October 2026, by regulation 14(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
7 Permitted activities: earth-wires, overhead telecommunication cables, and optical ground wires
(1)
Adding an earth-wire or overhead telecommunication cable or optical ground wires, or part of an earth-wire or overhead telecommunication cable or optical ground wires, to an existing transmission line is a permitted activity if the condition in subclause (5) is complied with.
(2)
Replacing an earth-wire or overhead telecommunication cable or optical ground wires, or part of an earth-wire or overhead telecommunication cable or optical ground wires, on an existing transmission line is a permitted activity if the condition in subclause (6) is complied with.
(3)
Maintaining an earth-wire or overhead telecommunication cable or optical ground wires on an existing transmission line is a permitted activity.
Conditions
(4)
[Revoked](5)
The diameter of a new wire or cable, or a new part of a wire or cable, must not exceed 30 millimetres.
(6)
The diameter of a replacement wire or cable, or a replacement part of a wire or cable, must not exceed—
(a)
the diameter of the existing wire, cable, or part (as the case may be); or
(b)
30 millimetres, if the diameter of the existing wire, cable, or part (as the case may be) is less than 30 millimetres.
Regulation 7 heading: amended, on 8 October 2026, by regulation 15(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(1): amended, on 8 October 2026, by regulation 15(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(1): amended, on 8 October 2026, by regulation 15(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(2): amended, on 8 October 2026, by regulation 15(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(3): amended, on 8 October 2026, by regulation 15(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(4): revoked, on 8 October 2026, by regulation 15(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(5): amended, on 8 October 2026, by regulation 15(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 7(6)(b): amended, on 8 October 2026, by regulation 15(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
8 Permitted activities: adding overhead circuits
(1)
Adding an overhead circuit to an existing transmission line is a permitted activity if—
(a)
the condition in subclause (2) is complied with; and
(b)
the condition in regulation 6(5) is complied with; and
(c)
all of the applicable conditions in regulation 10(2) to (8) are complied with.
Condition
(2)
The transmission line support structures of the transmission line must have been designed and built, at 14 January 2010, to carry the additional circuit.
Regulation 8(1)(b): amended, on 8 October 2026, by regulation 16(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 8(2): amended, on 8 October 2026, by regulation 16(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
9 Controlled activities
(1)
Adding an overhead conductor, or part of an overhead conductor, to an existing transmission line (except as part of adding an overhead circuit) is a controlled activity if—
(a)
the condition in regulation 6(5) is breached; but
(b)
all of the applicable conditions in regulation 10(2) to (8) are complied with.
(2)
Replacing an overhead conductor, or part of an overhead conductor, on an existing transmission line is a controlled activity if the condition in regulation 6(6) is breached.
(3)
Adding an earth-wire or overhead telecommunication cable or optical ground wire, or part of an earth-wire or overhead telecommunication cable or optical ground wire, to an existing transmission line is a controlled activity if the condition in regulation 7(5) is breached.
(4)
Replacing an earth-wire or overhead telecommunication cable or optical ground wire, or part of an earth-wire or overhead telecommunication cable or optical ground wire, on an existing transmission line is a controlled activity if the condition in regulation 7(6) is breached.
(5)
Adding an overhead circuit to an existing transmission line is a controlled activity if—
(a)
first,—
(i)
the condition in regulation 6(5) is breached; or
(ii)
the condition in regulation 8(2) is breached; and
(b)
second, all of the applicable conditions in regulation 10(2) to (8) are complied with.
Matters over which control reserved
(6)
Control is restricted to the following matters in relation to a controlled activity under this regulation:
(a)
visual effects:
(b)
the effects and timing of construction works:
(c)
the effects on services and infrastructure.
Regulation 9: replaced, on 8 October 2026, by regulation 17 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Increasing voltage or current rating, underground conductors, and undergrounding transmission lines
10 Permitted activities: increasing voltage or current rating
(1)
Increasing the voltage or current rating of an existing transmission line is a permitted activity if all of the applicable conditions in subclauses (2) to (9) are complied with.
Conditions
(2)
The electric and magnetic fields produced by the transmission of electricity at 50 Hz through overhead or underground alternating current transmission lines must, after being modelled in accordance with subclauses (4) to (7), be demonstrated to either—
(a)
not exceed the following reference levels for public exposure:
(i)
electric field strength of 5 kV/m; and
(ii)
magnetic flux density of 200 microteslas; or
(b)
not exceed the basic restriction level for electric and magnetic field exposure of 0.02 V/m in central nervous system tissues of the head and 0.4 V/m in all tissues of the head and body.
(3)
The static electric field strength produced by the transmission of electricity through overhead direct current transmission lines must be demonstrated to have no likely adverse human health effects after—
(a)
modelling the field strength in accordance with subclauses (4) to (6) as if references to electric field strength were references to static electric field strength; and
(b)
including the likely contribution to the field strength from the space charge around the transmission line caused by corona discharge.
(4)
The electric field strength and magnetic flux density of a transmission line must be modelled at whichever of the following locations is closest to the line:
(a)
1 metre above the ground in an area above, below, or next to the line that is reasonably accessible to the public; or
(b)
1 metre above the highest floor level of an occupied building.
(5)
The electric field strength and magnetic flux density of a transmission line may be modelled to take account of any shielding effect from buildings.
(6)
The electric field strength and magnetic flux density of an overhead transmission line must be modelled to result in the highest electric and magnetic fields likely under the following conservative climatic conditions to determine conductor position:
(a)
ambient temperature of 20°C in winter and 30°C in summer:
(b)
maximum solar radiation of 1 000 W/m²:
(c)
dry conditions:
(d)
wind speed of 0.6 m/s.
(7)
The magnetic flux density of an underground transmission line must be modelled to result in the highest magnetic field likely under conservative climatic conditions.
(8)
The results of modelling the electric field strength, magnetic flux density, density of electric current induced in the body, or static electric field strength under this regulation must be provided to the relevant territorial authority if requested by the territorial authority.
(9)
Existing transmission lines operating at 220 kV in a simplex configuration must comply with regulation 10A.
Regulation 10(2)(a)(ii): amended, on 8 October 2026, by regulation 18(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 10(2)(b): replaced, on 8 October 2026, by regulation 18(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 10(6): amended, on 8 October 2026, by regulation 18(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 10(7): amended, on 8 October 2026, by regulation 18(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 10(9): replaced, on 8 October 2026, by regulation 18(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
10A Permitted activity condition: modelled conductor noise
(1)
Modelled conductor noise levels must not exceed 45 dB LAeq(15min) at any assessment point above any building used for a sensitive activity that is occupied overnight.
(2)
An assessment point is the height above ground level calculated in accordance with the following formula:
1 metre + (n × 3 metres)
where n is the number of storeys of the building used for the sensitive activity, with the ground floor counted as the first storey.
(3)
If the limit in subclause (1) is exceeded,—
(a)
the best practicable option must be used to minimise noise; and
(b)
any new conductors must have—
(i)
a clean, matt surface finish that is free from grease; or
(ii)
trapezoidal-shaped strands; or
(iii)
a strand geometry and surface treatment proven to mitigate tonal noise during operation.
(4)
If subclause (3) applies, the assessment of the best practicable option must be provided to the relevant territorial authority if requested by the territorial authority.
(5)
A rule in a district plan may be more lenient than subclause (1).
Regulation 10A: inserted, on 8 October 2026, by regulation 19 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
11 Permitted activities: underground conductors
(1)
Adding an underground conductor, or part of an underground conductor, to an existing transmission line is a permitted activity if all of the applicable conditions in regulation 10(2) to (8) are complied with.
(2)
Replacing an underground conductor, or part of an underground conductor, on an existing transmission line is a permitted activity.
(3)
Maintaining an underground conductor on an existing transmission line is a permitted activity.
12 Controlled activities: undergrounding transmission lines
(1)
Undergrounding an existing transmission line is a controlled activity if all of the applicable conditions in regulation 10(2) to (8) are complied with.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the location of termination structures, and the route of underground cables, in relation to—
(i)
visual, landscape, and ecological effects; and
(ii)
the effects on a historic heritage place or area; and
(b)
the extent and nature of earthworks and control of sediment; and
(c)
the effects and timing of construction works; and
(d)
the effects on services and infrastructure.
Regulation 12(2)(a)(ii): amended, on 8 October 2026, by regulation 20 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
13 Non-complying activities
(1)
Each of the following activities is a non-complying activity if 1 or more of the applicable conditions in regulation 10(2) to (8) are breached:
(a)
adding an overhead conductor, or part of an overhead conductor, to an existing transmission line:
(b)
adding an overhead circuit to an existing transmission line:
(c)
increasing the voltage or current rating of an existing transmission line:
(d)
adding an underground conductor, or part of an underground conductor, to an existing transmission line:
(e)
undergrounding an existing transmission line.
(2)
Altering, relocating, or replacing a transmission line support structure of an existing transmission line (other than as part of a temporary line deviation or undergrounding) is a non-complying activity if 1 or more of the applicable conditions in regulation 10(2) to (8) are breached.
Regulation 13(2): replaced, on 8 October 2026, by regulation 21 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Transmission line support structures: Alteration, relocation, and replacement
14 Permitted activities
(1)
Altering, relocating, or replacing a tower of an existing transmission line (other than as part of a temporary line deviation or undergrounding) is a permitted activity if all of the applicable conditions in subclauses (3) to (5) are complied with.
(2)
Altering, relocating, or replacing a pole of an existing transmission line (other than as part of a temporary line deviation or undergrounding) is a permitted activity if all of the applicable conditions in subclauses (3), (4), and (8) are complied with.
Conditions
(3)
If a transmission line support structure is increased in height (including by being replaced with another structure),—
(a)
the structure may be made no more than 25% higher than its height as at 14 January 2010; and
(b)
the additional height must comply with any height restrictions for airport purposes specified in a district rule.
(4)
A transmission line support structure must not be relocated, or replaced with another transmission line support structure, so that any part of the structure at ground level is—
(a)
within 12 metres of an occupied building (measured from the closest point); or
(b)
any closer to an occupied building, if the existing structure is within 12 metres of the building (measured from the closest point).
(5)
If a tower is widened (including by being replaced with another tower), the length of each side of the tower’s footprint may not be increased by more than 25% as compared with the length of each side of the tower’s footprint as at 14 January 2010.
(6)
[Revoked](7)
[Revoked](8)
A pole must not be relocated, or replaced with another pole, more than 10 metres from the position the pole was in as at 14 January 2010 (measured horizontally).
Regulation 14(1): amended, on 8 October 2026, by regulation 22(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(2): amended, on 8 October 2026, by regulation 22(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(3)(a): amended, on 8 October 2026, by regulation 22(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(3)(b): amended, on 8 October 2026, by regulation 22(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(4)(a): amended, on 8 October 2026, by regulation 22(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(4)(b): amended, on 8 October 2026, by regulation 22(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(5): replaced, on 8 October 2026, by regulation 22(6) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(6): revoked, on 8 October 2026, by regulation 22(7) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(7): revoked, on 8 October 2026, by regulation 22(7) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 14(8): amended, on 8 October 2026, by regulation 22(8) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
15 Controlled activities
(1)
Altering, relocating, or replacing a tower of an existing transmission line (other than as part of a temporary line deviation or undergrounding) is a controlled activity if 1 or more of the conditions in regulation 14(3) to (5) are breached.
(2)
Altering, relocating, or replacing a pole of an existing transmission line (other than as part of a temporary line deviation or undergrounding) is a controlled activity if 1 or more of the conditions in regulation 14(3), (4), and (8) are breached.
(3)
Altering, relocating, or replacing a tower or pole of an existing transmission line as part of undergrounding, so that the tower or pole becomes a termination structure, is a controlled activity if all of the applicable conditions in regulation 14(3) and (4) are complied with.
Matters over which control reserved
(4)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
visual, landscape, and ecological effects; and
(b)
the effects on a historic heritage place or area; and
(c)
the effects and timing of construction works; and
(d)
the effects on services and infrastructure.
Regulation 15(1): replaced, on 8 October 2026, by regulation 23(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 15(2): replaced, on 8 October 2026, by regulation 23(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 15(3): amended, on 8 October 2026, by regulation 23(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 15(4)(b): amended, on 8 October 2026, by regulation 23(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
16 Restricted discretionary activities
[Revoked]Regulation 16: revoked, on 8 October 2026, by regulation 24 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Temporary structures and temporary line deviation
17 Permitted activities
(1)
Erecting or using a temporary structure in relation to an existing transmission line, or carrying out a temporary line deviation of an existing transmission line, is a permitted activity if the condition in subclause (2) is complied with.
Condition
(2)
Temporary structures and structures required for a temporary line deviation must not be in place for more than 12 months.
Regulation 17: replaced, on 8 October 2026, by regulation 25 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
18 Controlled activities
(1)
Erecting or using a temporary structure in relation to an existing transmission line, or carrying out a temporary line deviation of an existing transmission line, is a controlled activity if the condition in regulation 17(2) is breached.
(2)
[Revoked]Matters over which control reserved
(3)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the duration of any works; and
(b)
the effects and timing of construction works.
Regulation 18(1): replaced, on 8 October 2026, by regulation 26 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 18(2): revoked, on 8 October 2026, by regulation 26 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Transmission lines: Removal
19 Permitted activities
(1)
Removing an existing transmission line, or part of an existing transmission line, is a permitted activity if both of the conditions in subclauses (2) and (3) are complied with.
Conditions
(2)
The transmission line, or the part of the transmission line, and any associated construction or demolition material must be removed from the land.
(3)
Any ground that is disturbed from the removal must be restored in a way that minimises the risk of soil erosion, sediment run-off, and weed invasion.
20 Controlled activities
(1)
Removing an existing transmission line, or part of an existing transmission line, is a controlled activity if 1 or both of the conditions in regulation 19(2) and (3) are breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
restoration of the land; and
(b)
the effects and timing of removal works; and
(c)
the effects on services and infrastructure.
Regulation 20(2)(a): amended, on 8 October 2026, by regulation 27(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 20(2)(b): amended, on 8 October 2026, by regulation 27(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 20(2)(c): inserted, on 8 October 2026, by regulation 27(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Telecommunication devices
21 Permitted activities
(1)
Installing or modifying a telecommunication device on a transmission line support structure of an existing transmission line is a permitted activity.
(2)
Maintaining a telecommunication device on a transmission line support structure of an existing transmission line is a permitted activity.
(3)
[Revoked](4)
[Revoked]Regulation 21(1): amended, on 8 October 2026, by regulation 28(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 21(3) heading: revoked, on 8 October 2026, by regulation 28(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 21(3): revoked, on 8 October 2026, by regulation 28(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 21(4): revoked, on 8 October 2026, by regulation 28(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
22 Restricted discretionary activities
[Revoked]Regulation 22: revoked, on 8 October 2026, by regulation 29 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 2—Other electricity network activities
Subpart 2 heading: inserted, on 8 October 2026, by regulation 30 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Signs
23 Permitted activities
Installing or modifying a sign on or next to a support structure of a distribution line or an existing transmission line for the purpose of identifying the structure or its owner, or helping with safety or navigation, is a permitted activity.
Regulation 23: replaced, on 8 October 2026, by regulation 31 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
24 Restricted discretionary activities
[Revoked]Regulation 24: revoked, on 8 October 2026, by regulation 32 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Transmission line support structures: Discharges from blasting and applying protective coatings
25 Permitted activities
(1)
Blasting a support structure of a distribution line or an existing transmission line, or preparing the structure to receive protective coatings, including by removing impurities or corrosion using hand-held tools with an abrasive surface, is a permitted activity if—
(a)
all of the applicable conditions in subclauses (4) to (9) are complied with; or
(b)
the activity relates to abrasive blasting and the abrasive blasting is carried out in accordance with—
(i)
an environmental management plan that meets the requirements of regulation 25A; and
(ii)
a site-specific management plan that meets the requirements of regulation 25B.
(2)
Applying protective coatings to a transmission line support structure of an existing transmission line is a permitted activity if the condition in subclause (10) is complied with.
Conditions
(3)
[Revoked](4)
Wet abrasive blasting must not be done within 20 metres of—
(a)
a water body; or
(b)
the coastal marine area; or
(c)
a public road; or
(d)
an occupied building.
(5)
Abrasive material used in abrasive blasting must contain no more than 5% free silica by dry weight.
(6)
Waste and debris resulting from abrasive blasting must be removed from the site of the blasting to the extent practicable.
(7)
Dry abrasive blasting—
(a)
must be done no more than 2 metres above ground level; and
(b)
may be done only if covers or screens are used to mitigate the effects of any contaminants discharged by the blasting; and
(c)
must not be done within—
(i)
10 metres of a water body, the coastal marine area, or a public road; or
(ii)
20 metres of an occupied building.
(8)
If abrasive blasting is done on a tower coated with lead-based paint, the waste and debris (including abrasive material) resulting from the blasting must be captured and removed by using geotextile material of a filter quality or by any equivalent method.
(9)
The following substances must not be used for surface preparation: paint strippers (unless used on a solvent rag to degrease a surface), fungicides, acids, alkalis, sodium hypochlorite, or any other oxidising agent.
(10)
Protective coatings must be applied—
(a)
by hand; or
(b)
by pressurised spray used no more than 1 metre above ground level.
Regulation 25(1): replaced, on 8 October 2026, by regulation 33(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 25(3): revoked, on 8 October 2026, by regulation 33(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 25(4): replaced, on 8 October 2026, by regulation 33(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 25(7)(a): amended, on 8 October 2026, by regulation 33(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 25(7)(c): inserted, on 8 October 2026, by regulation 33(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
25A Environmental management plan
(1)
An environmental management plan must be provided to the relevant regional council at least 10 days before work is due to commence.
(2)
The environmental management plan must include the following information (if relevant to the activity):
(a)
the activities covered by the environmental management plan:
(b)
how the effects associated with those activities will be managed:
(c)
mitigation measures and when they will be deployed:
(d)
procedures covering incident management, complaints, spill management, and management of compressors:
(e)
protocols for giving notice, including to roading authorities, landowners, and the public:
(f)
opportunities for use of technologies that will allow for continuous environmental improvement:
(g)
a process for reviewing the environmental management plan:
(h)
a process for providing updates to the relevant regional council as necessary:
(i)
blasting information sheets:
(j)
any other relevant information.
(3)
If there are material amendments to the environmental management plan,—
(a)
the amendments must be documented and dated; and
(b)
the regional council must be advised that an amendment has been made; and
(c)
the amended environmental management plan must be made available to the regional council on request.
(4)
The regional council must be notified within 5 working days after works undertaken in accordance with the environmental management plan are completed.
(5)
The environmental management plan must be provided to the regional council annually if requested by the regional council.
(6)
In this regulation, material amendment means any significant change to blasting materials, technologies, procedures, and mitigation measures, or changes to the way effects associated with blasting will be managed as required by subclause (2)(b), that would significantly change the methods used to manage environmental effects.
Regulation 25A: inserted, on 8 October 2026, by regulation 34 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
25B Site-specific management plan
(1)
A site-specific management plan must be provided to the relevant regional council at least 10 days before work is due to commence.
(2)
The site-specific management plan must include the following information (if relevant to the activity):
(a)
the support structure name and location, including address and co-ordinates:
(b)
a map showing the proximity of the support structure to—
(i)
water bodies (including natural inland wetlands) and the coastal marine area, and stating the significance and special features of the water bodies (if applicable); and
(ii)
public roads; and
(iii)
occupied buildings:
(c)
whether the support structure has previously been painted with lead, and, if so, details of the blasting method and mitigation required:
(d)
the proposed methodology for the activity, including removing impurities or corrosion using hand-held tools with an abrasive surface and abrasive blasting:
(e)
the timing and duration of work:
(f)
mitigation measures and when they will be deployed, including reasons for not deploying mitigation measures if it is not practicable to do so:
(g)
the proposed monitoring processes:
(h)
how waste, including solvent rags, and debris will be managed and disposed of:
(i)
protocols for giving notice, including to roading authorities, landowners, and the public:
(j)
the location of plant and machinery, containment area of paints, and available spill kits:
(k)
procedures for recording and managing complaints:
(l)
roles, responsibilities, and quality assurance processes for environmental controls as required by paragraphs (a) to (k), if applicable.
(3)
The relevant regional council must be notified within 5 working days after works undertaken in accordance with the site-specific management plan are completed.
Regulation 25B: inserted, on 8 October 2026, by regulation 34 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
26 Controlled activities
(1)
Blasting a support structure of an existing transmission line or a support structure of a distribution line, or preparing the structure to receive protective coatings, including by removing impurities or corrosion using hand-held tools with an abrasive surface, is a controlled activity if—
(a)
1 or more of the applicable conditions in regulation 25(4) to (9) are breached; and
(b)
the abrasive blasting is not carried out in accordance with—
(i)
an environmental management plan that meets the requirements of regulation 25A; and
(ii)
a site-specific management plan that meets the requirements of regulation 25B.
(2)
Applying protective coatings to a support structure of a distribution line or an existing transmission line is a controlled activity if the condition in regulation 25(10) is breached.
Matters over which control reserved
(3)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the effects on water quality and ecologically-sensitive receiving environments; and
(b)
the effects on occupied buildings; and
(c)
the risk of contamination of soil; and
(d)
the effects on health; and
(e)
the effects on the use of public roads; and
(f)
the effects on services and infrastructure.
Regulation 26(1): replaced, on 8 October 2026, by regulation 35(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 26(2): amended, on 8 October 2026, by regulation 35(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 26(3)(e): inserted, on 8 October 2026, by regulation 35(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 26(3)(f): inserted, on 8 October 2026, by regulation 35(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
27 Restricted discretionary activities
[Revoked]Regulation 27: revoked, on 8 October 2026, by regulation 36 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Discharges to water
28 Permitted activities
(1)
Discharging contaminants into water, in relation to a distribution line or an existing transmission line, is a permitted activity if, after the water and contaminants are reasonably mixed together, all of the conditions in subclauses (2) to (6) are complied with.
Conditions
(2)
The discharge must not produce conspicuous—
(a)
films of oil or grease; or
(b)
scums or foams; or
(c)
floatable or suspended materials.
(3)
The discharge must not create a conspicuous change in colour or visual clarity.
(4)
The discharge must not emit an objectionable odour.
(5)
The discharge must not make fresh water unsuitable for farm animals to drink.
(6)
The discharge must not have adverse effects on aquatic life that are more than minor.
Regulation 28(1): amended, on 8 October 2026, by regulation 37 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
29 Controlled activities
(1)
Discharging contaminants into water, in relation to a distribution line or an existing transmission line, is a controlled activity if, after the water and contaminants are reasonably mixed together, 1 or more of the conditions in regulation 28(2) to (6) are breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the effects on water quality; and
(b)
the effects on aquatic life; and
(c)
the effects on services and infrastructure.
Regulation 29(1): amended, on 8 October 2026, by regulation 38(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 29(2)(c): inserted, on 8 October 2026, by regulation 38(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Trimming, felling, and removing trees and vegetation
30 Permitted activities
(1)
Trimming, felling, or removing any tree or vegetation, in relation to a distribution line or an existing transmission line, is a permitted activity if all of the applicable conditions in subclauses (3) to (7) are complied with.
Conditions
(2)
[Revoked](3)
Subclause (4) applies if a tree or vegetation is located on any land where a regional plan controls the use of the land for the purpose of—
(a)
soil conservation; or
(b)
avoiding or mitigating natural hazards.
(4)
The relevant regional council must be given written notice containing the following information at least 5 working days before the felling or removal of any tree or vegetation, or as soon as practicable if the felling or removal relates to imminent safety concerns:
(a)
the area of the felling or removal, including the location of support structures within that area:
(b)
the timing and duration of works:
(c)
the relevant regional plan rule relating to soil conservation or avoiding or mitigating natural hazards.
(5)
The felling or removal of any tree or vegetation must not create or contribute to—
(a)
instability of a slope or another land surface; or
(b)
erosion of the bed or bank of a water body or the coastal marine area.
(6)
Debris resulting from the trimming, felling, or removal must not enter a water body or the coastal marine area.
(7)
Trees or vegetation located in a natural area, or any notable trees, must not be trimmed, felled, or removed unless—
(a)
the trimming, felling, or removal is to—
(i)
comply with the Electricity (Hazards from Trees) Regulations 2003; or
(ii)
provide for the operation, maintenance, or repair of existing access tracks; or
(iii)
prevent damage, or the threat of damage, to the electricity network; and
(b)
the trimming, felling, or removal is carried out by an ecologist, arborist, or other suitably qualified professional; and
(c)
written notice containing the following information is provided to the relevant local authority at least 5 working days before the trimming, felling, or removal occurs, or as soon as practicable if the trimming, felling, or removal relates to imminent safety concerns:
(i)
a description of the vegetation or tree affected:
(ii)
the measures that will be taken to mitigate adverse effects:
(iii)
the measures that will be taken to limit trimming and clearance to what is necessary:
(iv)
the timing and duration of the work.
Regulation 30(1): amended, on 8 October 2026, by regulation 39(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 30(1): amended, on 8 October 2026, by regulation 39(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 30(2): revoked, on 8 October 2026, by regulation 39(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 30(3): replaced, on 8 October 2026, by regulation 39(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 30(4): replaced, on 8 October 2026, by regulation 39(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 30(7): inserted, on 8 October 2026, by regulation 39(5) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
31 Controlled activities
(1)
Trimming, felling, or removing any tree or vegetation, in relation to a distribution line or an existing transmission line, is a controlled activity if—
(a)
1 or more of the conditions in regulation 30(3) to (6) are breached; but
(b)
the condition in regulation 30(7) is complied with, if applicable.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
replanting; and
(b)
disposal of trees and vegetation; and
(c)
visual, landscape, and ecological effects; and
(d)
the effects on services and infrastructure; and
(e)
control of erosion and sediment; and
(f)
the effects on water quality and the coastal marine area.
Regulation 31(1): replaced, on 8 October 2026, by regulation 40(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 31(2)(d): inserted, on 8 October 2026, by regulation 40(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 31(2)(e): inserted, on 8 October 2026, by regulation 40(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 31(2)(f): inserted, on 8 October 2026, by regulation 40(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
32 Restricted discretionary activities
(1)
Trimming or removing any tree or vegetation, in relation to a distribution line or an existing transmission line, is a restricted discretionary activity if the condition in regulation 30(7) is breached.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
replanting; and
(b)
disposal of trees and vegetation; and
(c)
control of erosion and sediment; and
(d)
visual, landscape, and ecological effects; and
(e)
the effects on drainage, flooding, and overland flow paths.
Regulation 32(1): replaced, on 8 October 2026, by regulation 41 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Earthworks
33 Permitted activities
(1)
Earthworks relating to a distribution line or an existing transmission line carried out by Transpower New Zealand Limited or an electricity distribution business (or persons acting under the direction of Transpower New Zealand Limited or an electricity distribution business) are a permitted activity if all of the conditions in subclauses (2) to (9) are complied with.
Conditions
(2)
Earthworks in a natural area or historic heritage place or area must not, in a calendar year, exceed—
(a)
50 cubic metres per support structure; or
(b)
100 cubic metres per existing access track.
(2A)
Land disturbance in a natural area or historic heritage place or area must not, in a calendar year, exceed 1,000 square metres per existing access track.
(3)
Erosion sediment control must be applied and maintained at the site of earthworks, during and after the earthworks, to avoid the adverse effects of sediment on water bodies and the coastal marine area.
(4)
All areas of soil exposed by the earthworks must be stabilised against erosion as soon as practicable after the earthworks end to avoid the adverse effects of sediment on water bodies and the coastal marine area.
(5)
The earthworks must not create or contribute to—
(a)
instability or subsidence of a slope or another land surface; or
(b)
erosion of the bed or bank of a water body or the coastal marine area; or
(c)
drainage problems or flooding of overland flow paths.
(6)
Soil or debris from the earthworks must not be placed where it can enter a water body or the coastal marine area.
(7)
Earthworks must not be carried out on the bed of a lake or river or in the coastal marine area.
(8)
Earthworks must not be carried out on an archaeological site unless they are carried out in accordance with the Heritage New Zealand Pouhere Taonga Act 2014.
(9)
Earthworks must not be carried out on land that a local authority has identified as containing, or possibly containing, contaminants that pose a risk to the environment.
Regulation 33(1): amended, on 8 October 2026, by regulation 42(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 33(2): replaced, on 8 October 2026, by regulation 42(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 33(2A): inserted, on 8 October 2026, by regulation 42(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 33(8): amended, on 8 October 2026, by regulation 42(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 33(8): amended, on 20 May 2014, by section 107 of the Heritage New Zealand Pouhere Taonga Act 2014 (2014 No 26).
34 Controlled activities
(1)
Earthworks relating to a distribution line or an existing transmission line are a controlled activity if—
(a)
1 or more of the conditions in regulation 33(2) to (8) are breached; but
(b)
the condition in regulation 33(9) is complied with.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the extent and nature of any disturbance; and
(b)
management of the earthworks and the methods used to carry out the earthworks; and
(c)
control of erosion, sediment, and instability of land, and restoration of the land; and
(d)
visual, landscape, and ecological effects; and
(e)
the effects on historic heritage places or areas; and
(f)
the effects on drainage, flooding, and overland flow paths; and
(g)
the timing and duration of earthworks; and
(h)
the effects on water quality and the coastal marine area; and
(i)
the effects on natural areas; and
(j)
the effects on services and infrastructure.
Regulation 34(1): replaced, on 8 October 2026, by regulation 43(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(c): amended, on 8 October 2026, by regulation 43(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(e): amended, on 8 October 2026, by regulation 43(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(g): inserted, on 8 October 2026, by regulation 43(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(h): inserted, on 8 October 2026, by regulation 43(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(i): inserted, on 8 October 2026, by regulation 43(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 34(2)(j): inserted, on 8 October 2026, by regulation 43(4) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
35 Restricted discretionary activities: historic heritage areas
[Revoked]Regulation 35: revoked, on 8 October 2026, by regulation 44 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
36 Restricted discretionary activities: potentially contaminated land
(1)
Earthworks relating to a distribution line or an existing transmission line are a restricted discretionary activity if the condition in regulation 33(9) is breached.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
restoration of the land; and
(b)
management of the earthworks and the methods used to carry out the earthworks; and
(c)
the extent and nature of any disturbance in relation to ecological and health effects.
Regulation 36(1): amended, on 8 October 2026, by regulation 45 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Noise and vibration from construction activity
37 Permitted activities
(1)
A construction activity relating to a distribution line or an existing transmission line is a permitted activity if both of the conditions in subclauses (2) and (3) are complied with.
Conditions
(2)
The noise from the construction activity must comply with New Zealand Standard NZS 6803:1999 Acoustics—Construction Noise.
(3)
The vibrations from the construction activity must comply with the peak particle velocity limits in table 1 of German Standard DIN 4150–3:1999 Structural Vibration—Effects of Vibration on Structures.
Regulation 37(1): amended, on 8 October 2026, by regulation 46 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
38 Controlled activities
(1)
A construction activity relating to a distribution line or an existing transmission line is a controlled activity if 1 or both of the conditions in regulation 37(2) and (3) are breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the timing of the works; and
(b)
the effects on sensitive activities; and
(c)
the giving of notice of the works to parties who may be affected; and
(d)
the effects on services and infrastructure.
Regulation 38(1): amended, on 8 October 2026, by regulation 47(1) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 38(2)(b): amended, on 8 October 2026, by regulation 47(2) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Regulation 38(2)(d): inserted, on 8 October 2026, by regulation 47(3) of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Application of rules
Heading: inserted, on 8 October 2026, by regulation 48 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
38A Rules may be more lenient
A rule in a plan that applies to electricity distribution may be more lenient than the regulations in this subpart that relate to electricity distribution.
Regulation 38A: inserted, on 8 October 2026, by regulation 48 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 3—Other discretionary activities
Subpart 3 heading: inserted, on 8 October 2026, by regulation 49 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Other transmission activities[Revoked]
Heading: revoked, on 8 October 2026, by regulation 50 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
39 Discretionary activities
An electricity transmission network activity to which regulations 4 and 5 to 38 apply is a discretionary activity if it is not described in these regulations as a permitted activity, controlled activity, restricted discretionary activity, or non-complying activity.
Regulation 39: amended, on 8 October 2026, by regulation 51 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 4—Electric vehicle charging infrastructure
Subpart 4 heading: inserted, on 8 October 2026, by regulation 52 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Electric vehicle charging infrastructure[Revoked]
Heading: revoked, on 8 October 2026, by regulation 53 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
40 Permitted activities: electric vehicle charging infrastructure not available for public use
(1)
The construction, maintenance, operation, upgrade, replacement, and removal of electric vehicle charging infrastructure that is not available for public use is a permitted activity if the condition in subclause (2) is complied with.
Condition
(2)
Electric vehicle charging infrastructure that is not available for public use must comply with the zone rules relating to the construction of buildings and structures, and alterations and additions to existing buildings and structures, in a plan.
Regulation 40: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
41 Permitted activities: electric vehicle charging infrastructure on transport corridor
(1)
The construction, maintenance, operation, upgrade, replacement, and removal of electric vehicle charging infrastructure located on a transport corridor is a permitted activity if the condition in subclause (2) is complied with.
Condition
(2)
The electric vehicle charging infrastructure must be associated with a permitted or consented vehicle parking space.
Regulation 41: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
42 Permitted activities: electric vehicle charging infrastructure ancillary to primary activity
(1)
The construction, maintenance, operation, upgrade, replacement, and removal of electric vehicle charging infrastructure that is ancillary to the primary activity (excluding residential uses) on the site is a permitted activity if the applicable conditions in subclauses (2) to (6) are complied with.
Conditions
(2)
The electric vehicle charging infrastructure must not exceed 3 metres in height if located within—
(a)
1 metre of any front boundary; or
(b)
3 metres of any boundary adjoining a residential zone.
(3)
The electric vehicle charging infrastructure must be associated with a permitted or consented vehicle parking space.
(4)
In a residential zone, noise associated with an electric vehicle charging infrastructure activity must not exceed the following limits measured at the boundary of another site:
(a)
50 dB LAeq(15min) between 7 am and 10 pm:
(b)
40 dB LAeq(15min) between 10 pm and 7 am:
(c)
65 dB LAFmax between 10 pm and 7 am.
(5)
In a non-residential zone, noise associated with an electric vehicle charging infrastructure activity must not exceed the following limits measured—
(a)
at the boundary of any site zoned residential:
(i)
55 dB LAeq(15min) between 7 am and 10 pm:
(ii)
45 dB LAeq(15min) between 10 pm and 7 am:
(iii)
65 dB LAFmax between 10 pm and 7 am:
(b)
at the boundary of any site that is not zoned residential:
(i)
60 dB LAeq(15min) at any time:
(ii)
65 dB LAFmax between 10 pm and 7 am.
(6)
Earthworks associated with an electric vehicle charging infrastructure activity must—
(a)
not result in a permanent cut height of more than 1.5 metres; and
(b)
not result in a fill depth of more than 1.5 metres; and
(c)
be carried out with controls to minimise the mobilisation of silt or sediment beyond the boundary of the site where the earthworks occur; and
(d)
not result in any instability of land at or beyond the boundary of the site where the earthworks occur; and
(e)
be reinstated to stabilise the site from further erosion within 1 month after the earthworks are complete.
Regulation 42: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
43 Permitted activities: stand-alone electric vehicle charging infrastructure
(1)
The construction, maintenance, operation, upgrade, replacement, and removal of stand-alone electric vehicle charging infrastructure that is the primary activity (excluding residential uses) on the site is a permitted activity if—
(a)
the applicable conditions in subclauses (2) to (4) are complied with; and
(b)
the applicable conditions in regulation 42(4) to (6) are complied with.
Conditions
(2)
The site of the electric vehicle charging infrastructure must not be located in a residential zone, natural area, or historic heritage place or area.
(3)
The electric vehicle charging infrastructure must not exceed 3 metres in height if located within—
(a)
1 metre of any front boundary; or
(b)
3 metres of any boundary adjoining a residential zone.
(4)
No more than 10 vehicles per hour (averaged across 24 hours) can be charged at the site of the electric vehicle charging infrastructure.
Regulation 43: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Regulation 43(2): amended, on 8 October 2026, by regulation 54 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
44 Restricted discretionary activities
(1)
The construction, maintenance, operation, upgrade, replacement, and removal of electric vehicle charging infrastructure is a restricted discretionary activity if the applicable conditions in regulations 40, 42, and 43 are breached.
Matters to which discretion restricted
(2)
In relation to a restricted discretionary activity under this regulation, discretion is restricted to—
(a)
the following matters, to the extent that they relate to the breach of the relevant condition(s):
(i)
the effects on the safe and efficient operation of transport networks; and
(ii)
the effects of the operation of the activity, including noise; and
(b)
the extent to which a non-compliance is due to evolving technology; and
(c)
the proposed measures to avoid, mitigate, or remedy any adverse environmental effects.
Regulation 44: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
45 Rules may be more lenient
A rule in a plan that applies to electric vehicle charging infrastructure may be more lenient than the rules in regulations 40 to 44.
Regulation 45: inserted, on 7 May 2026, by regulation 9 of the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 (SL 2026/77).
Subpart 5—Electricity distribution
Subpart 5: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Operation and maintenance of distribution lines, use of access tracks, or occupation of land
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
46 Permitted activities
(1)
The operation of a distribution line is a permitted activity.
(2)
The maintenance of a distribution line is a permitted activity unless the maintenance activity is covered by another regulation.
(3)
The use of an access track to a distribution line or a cabinet is a permitted activity.
(4)
The occupation of land for a distribution line or a cabinet is a permitted activity.
Regulation 46: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Temporary structures and temporary line deviations
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
47 Permitted activities
(1)
Erecting or using a temporary structure or carrying out a temporary line deviation of an existing electricity distribution line or cabinet is a permitted activity if the condition in subclause (2) is complied with.
Condition
(2)
A temporary structure and a temporary line deviation must not be in place for more than 12 months.
Regulation 47: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
48 Controlled activities
(1)
Erecting or using a temporary structure or carrying out a temporary line deviation of an existing electricity distribution line or cabinet is a controlled activity if the condition in regulation 47(2) is breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the duration of any works:
(b)
the effects and timing of construction works.
Regulation 48: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Overhead conductors, circuits, earth-wires, overhead telecommunication cables, optical ground wires, telecommunication devices, and ancillary equipment on support structures
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
49 Permitted activities: overhead conductors, circuits, earth-wires, overhead telecommunication cables, and optical ground wires
(1)
Installing, adding, maintaining, modifying, or replacing an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, or part of an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, to a distribution line (including as part of the construction of a new distribution line support structure under regulation 61) is a permitted activity if—
(a)
both of the conditions in subclauses (2) and (3) are complied with; and
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Conditions
(2)
The diameter of a new earth-wire, telecommunication cable, or optical ground wire, or a new part of an earth-wire, telecommunication cable, or optical ground wire, must not exceed—
(a)
the diameter of the existing earth-wire, telecommunication cable, or optical ground wire (if applicable); or
(b)
30 millimetres, if there is no existing earth-wire, telecommunication cable, or optical ground wire, or if the existing diameter is less than 30 millimetres.
(3)
The diameter of a new conductor, or new part of a conductor, must not exceed—
(a)
the diameter of the existing conductor (if applicable); or
(b)
50 millimetres, if there is no existing conductor or if the diameter of the existing conductor is less than 50 millimetres.
Regulation 49: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
50 Permitted activities: telecommunication devices
(1)
Installing, modifying, or maintaining a telecommunication device on a distribution line support structure is a permitted activity if—
(a)
both of the conditions in subclauses (2) and (3) are complied with; and
(b)
all of the applicable conditions in regulation 70(2) to (4) are complied with.
Conditions
(2)
The telecommunication device must extend no more than 3.5 metres above the height of the distribution line support structure.
(3)
The width of the telecommunication device must not exceed 1.3 times the width of the distribution line support structure.
Regulation 50: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
51 Permitted activities: ancillary equipment on support structures
(1)
Installing, adding, or replacing ancillary equipment on support structures that relate to a distribution line, or modifying ancillary equipment on support structures that relate to a distribution line to increase the equipment’s size, is a permitted activity if—
(a)
the condition in subclause (3) is complied with; and
(b)
all of the applicable conditions in regulations 54, 69(2) to (8), and 70(2) to (4) are complied with.
(2)
Modifying ancillary equipment on support structures that relate to a distribution line (except if the modification increases the size of the ancillary equipment on support structures) is a permitted activity if all of the applicable conditions in regulations 54, 69(2) to (8), and 70(2) to (4) are complied with.
Condition
(3)
Ancillary equipment on support structures must not exceed 2 cubic metres per item.
Regulation 51: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
52 Controlled activities
(1)
Installing, adding, maintaining, modifying, or replacing an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, or part of an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, to a distribution line (including as part of the construction of a new distribution line support structure under regulation 61) is a controlled activity if—
(a)
either or both of the conditions in regulation 49(2) and (3) are breached; but
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
(2)
Installing, modifying, or maintaining a telecommunication device on a distribution line support structure is a controlled activity if—
(a)
either or both of the conditions in regulation 50(2) and (3) are breached; but
(b)
all of the applicable conditions in regulation 70(2) to (4) are complied with.
(3)
Installing, adding, or replacing ancillary equipment on support structures that relate to a distribution line, or modifying ancillary equipment on support structures that relate to a distribution line to increase the equipment’s size, is a controlled activity if—
(a)
either or both of the applicable conditions in regulations 51(3) and 54 are breached; but
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
(4)
Modifying ancillary equipment on support structures that relate to a distribution line (except if the modification increases the size of the ancillary equipment on support structures) is a controlled activity if—
(a)
the applicable condition in regulation 54 is breached; but
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Matters over which control reserved
(5)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the visual and landscape effects associated with the additional infrastructure:
(b)
the effects on services and infrastructure:
(c)
if applicable, the effects on sensitive activities from noise levels that are not compliant with regulation 54.
Regulation 52: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Cabinets
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
53 Permitted activities: new cabinets
(1)
Installing, operating, or maintaining a new cabinet on a transport corridor is a permitted activity if all of the applicable conditions in—
(a)
subclauses (2) to (4) are complied with; and
(b)
regulations 54, 69(2) to (8), and 70(2) to (4) are complied with.
Conditions
(2)
The cabinet must not be located in a natural area or historic heritage place or area.
(3)
The height of the cabinet must not exceed 2.5 metres.
(4)
The footprint of the cabinet must not exceed 6 square metres.
Regulation 53: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
54 Permitted activity condition: noise limits for cabinets and ancillary equipment on support structures
(1)
The noise from a cabinet or ancillary equipment on support structures that is located in a road reserve in or adjoining a residential zone must not exceed,—
(a)
between 7 am and 10 pm, 50 dB LAeq(5min); and
(b)
between 10 pm and 7 am,—
(i)
40 dB LAeq(5min); and
(ii)
65 dB LAFmax.
(2)
The noise from a cabinet or ancillary equipment on support structures that is located in a road reserve adjoining any other zone must not exceed,—
(a)
at any time, 60 dB LAeq(5min); and
(b)
between 10 pm and 7 am, 65 dB LAFmax.
(3)
If a cabinet or ancillary equipment on support structures is located outside of a road reserve, the cabinet or ancillary equipment on support structures must be installed and operated in accordance with the relevant rules about noise in the relevant district plan.
Regulation 54: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
55 Restricted discretionary activity: new cabinets
(1)
Installing, operating or maintaining a new cabinet on a transport corridor is a restricted discretionary activity if—
(a)
either—
(i)
1 or more of the conditions in regulation 53(2) to (4) are breached; or
(ii)
the applicable condition in regulation 54 is breached; but
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
visual and landscape effects:
(b)
ecological effects:
(c)
the effects on any natural area or historic heritage place or area:
(d)
the proposed methods of mitigating adverse effects:
(e)
the effects on services and infrastructure:
(f)
the effects on health and safety:
(g)
if applicable, the effects on sensitive activities from noise levels that are not compliant with regulation 54.
Regulation 55: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Overhead electricity distribution network assets
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
56 Permitted activities: overhead distribution lines
(1)
Altering, relocating, or replacing an overhead existing distribution line is a permitted activity if all of the applicable conditions in subclauses (3) to (10) are complied with.
(2)
Removing an overhead distribution line is a permitted activity if the condition in subclause (10) is complied with.
Conditions
(3)
The support structure must be located—
(a)
on a transport corridor; or
(b)
outside a natural area or historic heritage place or area.
(4)
The height of a support structure (including when replaced with another support structure)—
(a)
on a transport corridor must not exceed the following heights:
(i)
15 metres, if located within or adjoining a residential zone or Māori purpose zone:
(ii)
25 metres, if located within or adjoining a rural zone or industrial zone:
(iii)
20 metres, if located in any other zone; and
(b)
outside of a transport corridor must not exceed the following heights:
(i)
25 metres, if located within a rural zone or industrial zone; or
(ii)
20 metres, if located within a special purpose zone; or
(iii)
the height specified in the district plan rules, if located within a zone not specified in paragraph (a) or (b).
(5)
If a single pole is altered, relocated, or replaced with a new single pole, the width or diameter of the new pole must not be more than 1.5 times the width or diameter of the original pole at its largest point as at 8 October 2026.
(6)
If a single pole is replaced with a double pole, the width or diameter of the double pole must not be more than 2 times the width or diameter of the single pole at its largest point as at 8 October 2026.
(7)
If a double pole is altered, relocated, or replaced with a new double pole, the width or diameter of the double pole must not be more than 1.5 times the width or diameter of the double pole at its largest point as at 8 October 2026.
(8)
If an existing distribution line is relocated or replaced, the relocated or replaced distribution line must be located—
(a)
on land in the same planning zone as the existing distribution line; and
(b)
less than 10 metres from the location the distribution line was in as at 8 October 2026, unless the relocation or replacement is—
(i)
instructed by the relevant road controlling authority; or
(ii)
required for the purposes of road safety; or
(iii)
required to accommodate a third-party activity on the adjacent site and the support structure remains adjacent to the original site frontage.
(9)
Poles must not be replaced with towers.
(10)
Any land at the site of the existing distribution line that is disturbed from the alteration, relocation, or removal of an existing transmission line must be restored to its previous condition as soon as practicable and no later than 3 months after the alteration, relocation, or removal works are completed.
Regulation 56: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
57 Permitted activities: cabinets
(1)
Altering, relocating, or replacing an existing cabinet is a permitted activity if all of the applicable conditions in subclauses (3) to (8) are complied with.
(2)
Removing a cabinet is a permitted activity if the condition in subclause (8) is complied with.
Conditions
(3)
The cabinet must be located—
(a)
on a transport corridor; or
(b)
outside a natural area or historic heritage place or area.
(4)
The height of the cabinet (including when replaced with another cabinet) must not exceed—
(a)
2.5 metres, if the cabinet is located on a transport corridor; and
(b)
any height restriction in the relevant district plan rules, if the cabinet is located outside of a transport corridor.
(5)
The footprint of a cabinet located on a transport corridor (including when replaced with another cabinet) must not exceed 6 square metres.
(6)
The noise from the altered, relocated, or replaced cabinet must comply with regulation 54.
(7)
If an existing cabinet is relocated or replaced, the relocated or replaced cabinet must be located—
(a)
on land in the same planning zone as the existing cabinet; and
(b)
less than 10 metres from the location the cabinet was in as at 8 October 2026, unless the relocation or replacement is—
(i)
instructed by the relevant road controlling authority; or
(ii)
required for the purposes of road safety; or
(iii)
required to accommodate a third-party activity on the adjacent site and the support structure remains adjacent to the original site frontage.
(8)
Any land at the site of the existing cabinet that is disturbed from the alteration, relocation, or removal of an existing cabinet must be restored to its previous condition as soon as practicable and no later than 3 months after the alteration, relocation, or removal works are completed.
Regulation 57: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
58 Controlled activities: overhead existing distribution lines and cabinets
(1)
Altering, relocating, or replacing an overhead existing distribution line is a controlled activity if 1 or more of the applicable conditions in regulation 56(3) to (10) are breached.
(2)
Removing an overhead distribution line is a controlled activity if the condition in regulation 56(10) is breached.
(3)
Altering, relocating, or replacing an existing cabinet is a controlled activity if 1 or more of the applicable conditions in regulation 57(3) to (8) are breached.
(4)
Removing a cabinet is a controlled activity if the condition in regulation 57(8) is breached.
Matters over which control reserved
(5)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
visual, landscape, and ecological effects:
(b)
the effects on any natural area or historic heritage place or area:
(c)
the proposed methods of mitigating adverse effects:
(d)
restoration of the land:
(e)
the effects on services and infrastructure.
Regulation 58: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
59 Permitted activities: mid-span poles
(1)
Installing mid-span poles on an existing distribution line is a permitted activity if—
(a)
the condition in subclause (2) is complied with; and
(b)
the condition in regulation 56(4) is complied with.
Condition
(2)
A mid-span pole must not be located within a natural area or a historic heritage place or area (unless the existing distribution line is located in one of those places or areas).
Regulation 59: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
60 Controlled activities: mid-span poles
(1)
Installing mid-span poles on an existing electricity distribution line is a controlled activity if either or both of the conditions in regulations 56(4) and 59(2) are breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the visual and landscape effects:
(b)
the ecological effects:
(c)
the effects on any natural area or historic heritage place or area:
(d)
the proposed methods of mitigating adverse effects:
(e)
the effects on services and infrastructure:
(f)
the effects on health and safety.
Regulation 60: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
61 Permitted activities: distribution line support structures
(1)
Constructing support structures for a distribution line (except mid-span poles for an existing distribution line) is a permitted activity if—
(a)
the condition in subclause (2) is complied with; and
(b)
the applicable condition in regulation 56(4) is complied with.
Condition
(2)
The support structure must not be located in a natural area or a historic heritage place or area.
Regulation 61: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
62 Controlled activity: distribution line support structures
(1)
Constructing support structures for a distribution line (except mid-span poles for an existing distribution line) is a controlled activity if the distribution line is located on a transport corridor and either or both of the conditions in regulations 56(4) and 61(2) are breached.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the effects on any natural area or historic heritage place or area:
(b)
the proposed methods of mitigating adverse effects:
(c)
the effects on services and infrastructure.
Regulation 62: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
63 Restricted discretionary activity: distribution line support structures
(1)
Constructing support structures for a distribution line is a restricted discretionary activity if—
(a)
either or both of the conditions in regulations 56(4) and 61(2) are breached; and
(b)
the support structure is not located on a transport corridor.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
visual and landscape effects:
(b)
ecological effects:
(c)
the effects on any natural area or historic heritage place or area:
(d)
the proposed methods of mitigating adverse effects:
(e)
the effects on services and infrastructure:
(f)
the effects on health and safety.
Regulation 63: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Underground electricity distribution network assets
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
64 Permitted activities: undergrounding existing distribution line and replacing or maintaining underground distribution line
(1)
Undergrounding an overhead existing distribution line is a permitted activity if—
(a)
the condition in subclause (3) is complied with; and
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
(2)
Replacing or maintaining an underground distribution line is a permitted activity.
Condition
(3)
The existing distribution line must be located—
(a)
on a transport corridor; or
(b)
if it is not on a transport corridor, outside of a natural area or historic heritage place or area.
Regulation 64: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
65 Controlled activities: undergrounding existing distribution line
(1)
Undergrounding an overhead existing distribution line is a controlled activity if—
(a)
the condition in regulation 64(3) is breached; but
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the location of termination structures:
(b)
the route of underground cables in relation to effects on any natural area or historic heritage place or area, and visual effects:
(c)
the extent of earthworks and any technical requirements:
(d)
the effects and timing of construction:
(e)
the effects on services and infrastructure.
Regulation 65: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
66 Permitted activities: construction of underground distribution line
(1)
Constructing a new underground distribution line is a permitted activity if—
(a)
the condition in subclause (2) is complied with; and
(b)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Condition
(2)
A new underground distribution line must not be constructed within a natural area or a historic heritage place or area.
Regulation 66: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
67 Controlled activity: construction of underground distribution line
(1)
Constructing a new underground distribution line is a controlled activity if—
(a)
it is located on a transport corridor; and
(b)
the condition in regulation 66(2) is breached; but
(c)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the effects on any natural area or historic heritage place or area:
(b)
the proposed methods of mitigating adverse effects:
(c)
the effects on services and infrastructure.
Regulation 67: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
68 Restricted discretionary activity: construction of underground distribution line
(1)
Constructing a new underground distribution line is a restricted discretionary activity if—
(a)
it is located outside a transport corridor; and
(b)
the condition in regulation 66(2) is breached; but
(c)
all of the applicable conditions in regulations 69(2) to (8) and 70(2) to (4) are complied with.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
visual and landscape effects:
(b)
ecological effects:
(c)
the effects on any natural area or historic heritage place or area:
(d)
the proposed methods of mitigating adverse effects:
(e)
the effects on services and infrastructure:
(f)
the effects on health and safety.
Regulation 68: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Electric, magnetic, and radiofrequency fields
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
69 Permitted activities: generating or emitting electric or magnetic field
(1)
Generating or emitting an electric or a magnetic field from a component of the electricity distribution network is a permitted activity if all of the applicable conditions in subclauses (2) to (8) are complied with.
Conditions
(2)
The electric and magnetic fields produced by the distribution of electricity at 50 Hz through overhead or underground alternating current distribution lines must, after being modelled in accordance with subclauses (4) to (7), be demonstrated to—
(a)
not exceed the following reference levels for public exposure:
(i)
electric field strength of 5 kV/m; and
(ii)
magnetic flux density of 200 microteslas; or
(b)
not exceed the basic restriction level for electric and magnetic field exposure of 0.02 V/m in central nervous system tissues of the head and 0.4 V/m in all tissues of the head and body.
(3)
The static electric field strength produced by the distribution of electricity through overhead direct current distribution lines must be demonstrated to have no likely adverse human health effects after—
(a)
the field strength is modelled in accordance with subclauses (4) to (6) as if references to electric field strength were references to static electric field strength; and
(b)
the likely contribution to the field strength from the space charge around the distribution line caused by corona discharge is included.
(4)
The electric field strength and magnetic flux density of a distribution line must be modelled at whichever of the following locations is closer to the line:
(a)
1 metre above the ground in an area above, below, or next to the line that is reasonably accessible to the public:
(b)
1 metre above the highest floor level of an occupied building.
(5)
The electric field strength and magnetic flux density of a distribution line may be modelled to take account of any shielding effect from buildings.
(6)
The electric field strength and magnetic flux density of an overhead distribution line must be modelled to result in the highest electric and magnetic fields likely under conservative climatic conditions using the following climatic conditions to determine conductor position:
(a)
ambient temperature of 20°C in winter and 30°C in summer:
(b)
maximum solar radiation of 1,000 W/m²:
(c)
dry conditions:
(d)
wind speed of 0.6 m/s.
(7)
The magnetic flux density of an underground distribution line must be modelled to result in the highest magnetic field likely under conservative climatic conditions.
(8)
The results of modelling the electric field strength, magnetic flux density, density of electric current induced in the body, or static electric field strength under this regulation must be provided to the relevant territorial authority if requested by the territorial authority.
(9)
The territorial authority may request the information described in subclause (8) if it has just cause to believe that a component of the electricity distribution network could pose a risk to human health and safety.
Regulation 69: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
70 Permitted activities: generating or emitting radiofrequency field
(1)
Generating or emitting a radiofrequency field from a component of the electricity distribution network is a permitted activity if all of the conditions in subclauses (2) to (4) are complied with.
Conditions
(2)
The component of the electricity distribution network must be installed and operated in accordance with NZS 2772.1.
(3)
Before the component of the electricity distribution network becomes operational, the local authority must be given—
(a)
written or electronic notice of the distribution line’s location; and
(b)
a pre-commencement report that—
(i)
is prepared in accordance with AS/NZS 2772.2; and
(ii)
takes into account exposures arising from other distribution lines in the vicinity of the component of the electricity distribution network; and
(iii)
predicts whether the radiofrequency field levels at places in the vicinity of the component of the electricity distribution network that are reasonably accessible to the general public will comply with NZS 2772.1.
(4)
If the prediction referred to in subclause (3)(b)(iii) is that the radiofrequency field levels will reach at least 25% of the maximum level authorised by NZS 2772.1 for exposure of the general public, the local authority must be given a post-commencement report, within 3 months after the component of the electricity distribution network becomes operational, that—
(a)
is prepared in accordance with AS/NZS 2772.2; and
(b)
provides evidence that the actual radiofrequency field levels at places in the vicinity of the component of the electricity distribution network that are reasonably accessible to the general public comply with NZS 2772.1.
(5)
In this regulation,—
AS/NZS 2772.2 means AS/NZS 2772.2:2016 Radiofrequency fields—Part 2: Principles and methods of measurement and computation—3 kHz to 300 GHz
NZS 2772.1 means NZS 2772.1:1999 Radiofrequency fields—Maximum exposure levels—3 kHz to 300 GHz.
Regulation 70: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
71 Non-complying activities: generating or emitting electric, magnetic, or radiofrequency field
Each of the following activities is a non-complying activity if 1 or more of the applicable conditions in regulations 69(2) to (8) or 70(2) to (4) are breached:
(a)
generating or emitting an electric or a magnetic field from a distribution line:
(b)
generating or emitting a radiofrequency field from a distribution line:
(c)
installing, adding, maintaining, modifying, or replacing an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, or part of an overhead conductor, circuit, earth-wire, overhead telecommunication cable, or optical ground wire, to a distribution line:
(d)
installing, modifying, or maintaining a telecommunication device on a distribution line support structure:
(e)
installing, adding, replacing, or modifying ancillary equipment on support structures that relate to a distribution line:
(f)
installing, operating, or maintaining a new cabinet:
(g)
adding an overhead conductor, or part of an overhead conductor, to a new support structure for a distribution line:
(h)
undergrounding an overhead existing distribution line:
(i)
adding ancillary equipment on support structures:
(j)
constructing a new underground line.
Regulation 71: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Application of rules
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
72 Rules may be more lenient
A rule in a district plan that applies to electricity distribution may be more lenient than this subpart, except—
(a)
for regulations 69 to 71; and
(b)
if a part of a regulation requires compliance with regulation 69 or 70.
Regulation 72: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 6—National grid
Subpart 6: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
73 National grid definitions
(1)
The national grid subdivision corridor—
(a)
comprises the following areas either side of the centre line of overhead existing transmission lines:
(i)
14 metres for 66 kV transmission lines on single poles:
(ii)
16 metres for 66 kV transmission lines on pi poles:
(iii)
32 metres for 66 kV transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(iv)
14 metres for 110 kV transmission lines on single poles:
(v)
16 metres for 110 kV transmission lines on pi poles:
(vi)
32 metres for 110 kV transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(vii)
37 metres for 220 kV transmission lines:
(viii)
39 metres for 350 kV transmission lines:
(ix)
16 metres for the Benmore-Bog Roy A, Te Hikowhenua-Deviation A and South Makara-Oteranga Bay A transmission lines; but
(b)
does not include those parts of the electricity transmission network that are covered by a designation under Part 8 of the Act.
(2)
The national grid yard—
(a)
comprises the following areas:
(i)
10 metres either side of the centre line of 110 kV overhead existing transmission lines on single poles:
(ii)
10 metres either side of the centre line of 66 kV overhead existing transmission lines on single poles:
(iii)
10 metres either side of the centre line of 66 kV overhead existing transmission lines on pi poles:
(iv)
10 metres either side of the centre line of 66 kV overhead existing transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(v)
12 metres either side of the centre line of 110 kV overhead existing transmission lines on pi poles:
(vi)
12 metres either side of the centre line of 110 kV overhead existing transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(vii)
12 metres either side of the centre line of 220 kV overhead existing transmission lines on pi poles:
(viii)
12 metres either side of the centre line of 220 kV overhead existing transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(ix)
12 metres either side of the centre line of 350 kV overhead existing transmission lines on pi poles:
(x)
12 metres either side of the centre line of 350 kV overhead existing transmission lines on towers (including steel monopoles that replace steel-lattice towers):
(xi)
12 metres either side of the centre line of the Benmore-Bog Roy A and Te Hikowhenua-Deviation A existing transmission lines:
(xii)
10 metres either side of the centre line of the South Makara-Oteranga Bay A existing transmission line:
(xiii)
12 metres in any direction from the outer visible edge of an existing transmission line support structure; but
(b)
does not include those parts of the electricity transmission network that are covered by a designation under Part 8 of the Act.
Regulation 73: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
National grid yard: buildings, structures, and network utilities
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
74 Permitted activities: buildings and structures used for sensitive activities
(1)
Altering or adding to an existing building or structure used for a sensitive activity within the national grid yard is a permitted activity if the applicable conditions in subclauses (3), (7), and (8) are complied with.
(2)
Constructing accessory buildings used for sensitive activities within the national grid yard is a permitted activity if the applicable conditions in subclauses (4) to (8) are complied with.
Conditions
(3)
The alteration or addition must not involve an increase in the building height or area of land that the building occupies.
(4)
The accessory building must be located more than 12 metres from a national grid support structure.
(5)
The height of the accessory building must not exceed 2.5 metres.
(6)
The area of the accessory building must not exceed 10 square metres.
(7)
All activities, buildings, and structures must comply with the safe distance standards in NZECP 34:2001.
(8)
Activities, buildings, and structures must not permanently physically impede vehicle access to a national grid support structure.
Regulation 74: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
75 Permitted activities: network utilities
(1)
Any works undertaken by a network utility operator (as defined in section 166(1) of the Act) within the national grid yard and any activity related to the connection of electricity generation to the electricity transmission network within the national grid yard are permitted activities if both of the conditions in subclauses (2) and (3) are complied with.
Conditions
(2)
All works undertaken by a network utility operator must comply with the safe distance standards in NZECP 34:2001.
(3)
Activities, buildings, and structures must not permanently physically impede vehicle access to a national grid support structure.
Regulation 75: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
76 Permitted activities: fences
(1)
Constructing, altering, or maintaining fences within the national grid yard is a permitted activity if all of the applicable conditions in subclauses (2) to (4) are complied with.
Conditions
(2)
The fence must be located more than—
(a)
5 metres from a national grid pole; and
(b)
6 metres from a national grid tower.
(3)
All fences must comply with the safe distance standards in NZECP 34:2001.
(4)
Fences must not permanently physically impede vehicle access to a national grid support structure.
Regulation 76: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
77 Permitted activities: ancillary stockyards and platforms
(1)
Constructing, altering, or maintaining stockyards and platforms that are ancillary to farming activities, including those associated with milking sheds, within the national grid yard is a permitted activity if all of the applicable conditions in subclauses (2) to (4) are complied with.
Conditions
(2)
The ancillary stockyard or platform must be located more than 12 metres from a national grid support structure.
(3)
Ancillary stockyards and platforms must comply with the safe distance standards in NZECP 34:2001.
(4)
Ancillary stockyards and platforms must not permanently physically impede vehicle access to a national grid support structure.
Regulation 77: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
78 Permitted activities: uninhabited farm and horticultural buildings and structures
(1)
Constructing, altering, or maintaining uninhabited farm and horticultural buildings and structures within the national grid yard is a permitted activity if all of the applicable conditions in subclauses (2) to (4) are complied with.
Conditions
(2)
The uninhabited farm and horticultural building or structure must be located more than 12 metres from a national grid support structure.
(3)
Uninhabited farm and horticultural buildings and structures must comply with the safe distance standards in NZECP 34:2001.
(4)
Uninhabited farm and horticultural buildings and structures must not permanently physically impede vehicle access to a national grid support structure.
Regulation 78: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
79 Permitted activities: artificial crop protection structures and crop support structures
(1)
Constructing, altering, or maintaining artificial crop protection structures or crop support structures within the national grid yard is a permitted activity if all of the applicable conditions in subclauses (2) to (5) are complied with.
Conditions
(2)
Artificial crop protection structures and crop support structures must be located more than—
(a)
8 metres from a national grid pole; and
(b)
12 metres from a national grid tower.
(3)
If an artificial crop protection structure or crop support structure is located between 8 metres and 12 metres from a national grid pole,—
(a)
the artificial crop protection structure or crop support structure must—
(i)
not exceed a height of 2.5 metres; and
(ii)
be removable or temporary; and
(iii)
allow for—
(A)
a clear working space of 12 metres around the transmission line pole for maintenance; and
(B)
all-weather access to the transmission line pole; and
(C)
a sufficient area for maintenance equipment, including a crane; or
(b)
Transpower New Zealand Limited must have provided prior written consent for the construction, alteration, or maintenance of the artificial crop protection structure or crop support structure in accordance with NZECP 34:2001.
(4)
Artificial crop protection structures and crop support structures must comply with the safe distance standards in NZECP 34:2001.
(5)
Artificial crop protection structures and crop support structures must not permanently physically impede vehicle access to a national grid support structure.
Regulation 79: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
80 Non-complying activities
(1)
Each of the following activities is a non-complying activity if it is done within the national grid yard:
(a)
establishing sensitive activities in an existing building or a new building:
(b)
constructing, operating, using, or establishing—
(i)
wintering barns:
(ii)
commercial greenhouses:
(iii)
immoveable protective canopies:
(iv)
produce packing facilities:
(v)
milking sheds:
(vi)
buildings or structures for the handling or storage of hazardous substances with explosive or flammable intrinsic properties:
(vii)
any other building or structure that is not covered by regulations 74 to 79.
(2)
Subclause (1)(b)(vi) does not apply to the accessory use and storage of hazardous substances in domestic-scale quantities.
(3)
Altering or adding to an existing building or structure used for a sensitive activity within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 74(3), (7), and (8) are breached.
(4)
Constructing accessory buildings used for sensitive activities within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 74(4) to (8) are breached.
(5)
Any works undertaken by a network utility operator (as defined in section 166(1) of the Act) within the national grid yard and any activity related to the connection of electricity generation to the electricity transmission network within the national grid yard are non-complying activities if either or both of the applicable conditions in regulation 75(2) and (3) are breached.
(6)
Constructing, altering, or maintaining fences within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 76(2) to (4) are breached.
(7)
Constructing, altering, or maintaining stockyards and platforms that are ancillary to farming activities, including those associated with milking sheds, within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 77(2) to (4) are breached.
(8)
Constructing, altering, or maintaining uninhabited farm and horticultural buildings and structures within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 78(2) to (4) are breached.
(9)
Constructing, altering, or maintaining artificial crop protection structures or crop support structures within the national grid yard is a non-complying activity if 1 or more of the applicable conditions in regulation 79(2) to (5) are breached.
Regulation 80: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
National grid yard: earthworks, land disturbance, and vertical holes
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
81 Permitted activities
(1)
Carrying out earthworks or land disturbance, or excavating vertical holes, within the national grid yard is a permitted activity—
(a)
if all of the applicable conditions in subclauses (2) to (5) are complied with; or
(b)
if—
(i)
the condition in subclause (4) is complied with; and
(ii)
Transpower New Zealand Limited has provided prior written consent for the earthworks, land disturbance, or excavation of vertical holes in accordance with NZECP 34:2001.
Conditions
(2)
The earthworks, land disturbance, and excavation of vertical holes must not exceed the following depths:
(a)
300 millimetres, if the activity is carried out within 6 metres of the outer visible edge of a foundation of a national grid tower:
(b)
3 metres, if the activity is carried out between 6 metres and 12 metres from the outer visible edge of a foundation of a national grid tower:
(c)
300 millimetres, if the activity is carried out within 2.2 metres of the outer visible edge of a national grid pole:
(d)
750 millimetres, if the activity is carried out between 2.2 metres and 5 metres from the outer visible edge of a national grid pole.
(3)
The earthworks, land disturbance, and excavation of vertical holes must not compromise the stability of a national grid support structure.
(4)
The earthworks, land disturbance, and excavation of vertical holes must not result in a reduction in the ground to conductor clearance distances as required in table 4 of NZECP 34:2001.
(5)
The earthworks, land disturbance, and excavation of vertical holes must not permanently physically impede access to a national grid support structure.
When conditions do not apply
(6)
Subclause (2)(d) does not apply to the excavation of vertical holes if—
(a)
the hole is at least 1.5 metres from the outer visible edge of a national grid pole; and
(b)
the diameter of the hole is less than 500 millimetres.
(7)
Subclauses (2) and (5) do not apply to earthworks and land disturbance undertaken for the purpose of repairing or resealing a road, footpath, driveway, or farm track.
Regulation 81: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
82 Non-complying activities
Carrying out earthworks or land disturbance, or excavating vertical holes, within the national grid yard is a non-complying activity—
(a)
if—
(i)
1 or more of the applicable conditions in regulation 81(2) to (5) are breached; and
(ii)
Transpower New Zealand Limited has not provided prior written consent for the earthworks, land disturbance, or excavation of vertical holes in accordance with NZECP 34:2001; or
(b)
if the condition in regulation 81(4) is breached.
Regulation 82: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
National grid subdivision corridor: subdivisions
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
83 Restricted discretionary activities
(1)
Subdividing land within the national grid subdivision corridor is a restricted discretionary activity if—
(a)
a building platform for a new dwelling or principal building can be accommodated outside of the national grid yard; and
(b)
vehicle access to national grid support structures is maintained.
Matters to which discretion restricted
(2)
Discretion is restricted to the following matters in relation to a restricted discretionary activity under this regulation:
(a)
the extent to which the subdivision allows for earthworks, buildings, and structures to comply with the safe distance requirements of NZECP 34:2001:
(b)
the provision for the ongoing efficient operation, maintenance, upgrading, and development of electricity transmission network activities, including continued reasonable access to existing transmission lines:
(c)
the extent to which potential adverse effects (including visual and reverse sensitivity effects) are mitigated through the location of building platforms:
(d)
the extent to which the design of the subdivision allows for activities to be set back from the national grid to ensure that adverse effects on, and from, the national grid and on public safety and property are appropriately avoided, remedied, or mitigated, for example, through the location of roads and reserves under the transmission lines:
(e)
the nature and location of any vegetation proposed to be planted:
(f)
the outcome of any consultation with, and technical advice from, Transpower New Zealand Limited.
Regulation 83: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
84 Non-complying activities
Subdividing land within the national grid subdivision corridor is a non-complying activity if it is not carried out in accordance with the restricted discretionary activity standards in regulation 83(1)(a) and (b).
Regulation 84: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Subpart 7—Sites near or with distribution lines
Subpart 7: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Sites near distribution lines: buildings and structures
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
85 Permitted activities
(1)
Constructing a new building or structure, or altering or extending an existing building or structure, within 30 metres of an overhead distribution line is a permitted activity if both of the conditions in subclauses (2) and (3) are complied with.
Conditions
(2)
The construction, alteration, or extension activity must comply with the safe distance requirements in NZECP 34:2001.
(3)
Activities, buildings, and structures must not permanently physically impede vehicle access to a distribution line support structure.
Regulation 85: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
86 Discretionary activities
Constructing a new building or structure, or altering or extending an existing building or structure, within 30 metres of an overhead distribution line is a discretionary activity if either or both of the conditions in regulation 85(2) and (3) are breached.
Regulation 86: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Sites with distribution lines: earthworks, land disturbance, and vertical holes
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
87 Permitted activities
(1)
Carrying out earthworks or land disturbance, or excavating vertical holes, on a site containing an overhead distribution line is a permitted activity if—
(a)
the condition in subclause (2) is complied with; or
(b)
an electricity distribution business has provided prior written consent for the earthworks, land disturbance, or excavation of vertical holes in accordance with NZECP 34:2001.
Condition
(2)
The earthworks, land disturbance, and excavation of vertical holes must comply with NZECP 34:2001.
Regulation 87: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
88 Discretionary activities
Carrying out earthworks or land disturbance, or excavating vertical holes, on a site containing an overhead distribution line is a discretionary activity if—
(a)
the condition in regulation 87(2) is breached; and
(b)
an electricity distribution business has not provided prior written consent for the earthworks, land disturbance, or excavation of vertical holes in accordance with NZECP 34:2001.
Regulation 88: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Sites with distribution lines: boundary adjustments and subdivisions
Heading: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
89 Permitted activities: boundary adjustment
(1)
Carrying out a boundary adjustment on a site containing a distribution line is a permitted activity if the condition in subclause (2) is complied with.
Condition
(2)
Vehicle access to overhead distribution line support structures must be maintained.
Regulation 89: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
90 Discretionary activities: boundary adjustment
Carrying out a boundary adjustment on a site containing a distribution line is a discretionary activity if the condition in regulation 89(2) is breached.
Regulation 90: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
91 Controlled activities: subdivision
(1)
Subdividing land to create a new allotment on a site containing an overhead distribution line is a controlled activity if all buildings, structures, and building platforms comply with the minimum safe distance requirements in NZECP 34:2001.
Matters over which control reserved
(2)
Control is reserved over the following matters in relation to a controlled activity under this regulation:
(a)
the extent to which the subdivision allows for the anticipated future land use, earthworks, buildings, and structures to comply with the safe distance requirements provided in NZECP 34:2001, including the location of building platforms and site access:
(b)
the provision for the ongoing efficient operation, maintenance, and upgrading of a distribution line, including continued reasonable access for maintenance, inspections, and upgrading:
(c)
the outcome of consultation with the owner and operator of the distribution line:
(d)
the measures necessary to avoid or sufficiently minimise the adverse effects, including health and safety risks, of the overhead distribution lines on future owners and occupiers of the sites that result from the subdivision.
Regulation 91: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
92 Discretionary activities: subdivision
Subdividing land to create a new allotment on a site containing a distribution line is a discretionary activity if the minimum safe distance requirements in NZECP 34:2001 are breached.
Regulation 92: inserted, on 8 October 2026, by regulation 55 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Schedule 1 Transitional, savings, and related provisions
Schedule 1: replaced, on 8 October 2026, by regulation 56 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Part 1 Provision relating to Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Amendment Regulations 2026 and Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026
Schedule 1 Part 1: inserted, on 8 October 2026, by regulation 56 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
1 References to previous Titles
Every reference in any enactment and in any document to the Resource Management (National Environmental Standards for Electricity Transmission and Electric Vehicle Charging Infrastructure Activities) Regulations 2009, and to the Resource Management (National Environmental Standards for Electricity Transmission Activities) Regulations 2009, must, unless the context otherwise provides, be read as a reference to the Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009.
Schedule 1 clause 1: inserted, on 8 October 2026, by regulation 56 of the Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260).
Rebecca Kitteridge,
Clerk of the Executive Council.
Issued under the authority of the Legislation Act 2019.
Date of notification in Gazette: 17 December 2009.
Notes
1 General
This is a consolidation of the Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009 that incorporates the amendments made to the legislation so that it shows the law as at its stated date.
2 Legal status
A consolidation is taken to correctly state, as at its stated date, the law enacted or made by the legislation consolidated and by the amendments. This presumption applies unless the contrary is shown.
Section 78 of the Legislation Act 2019 provides that this consolidation, published as an electronic version, is an official version. A printed version of legislation that is produced directly from this official electronic version is also an official version.
3 Editorial and format changes
The Parliamentary Counsel Office makes editorial and format changes to consolidations using the powers under subpart 2 of Part 3 of the Legislation Act 2019. See also PCO editorial conventions for consolidations.
4 Amendments incorporated in this consolidation
Resource Management (National Environmental Standards for Electricity Network Activities) Amendment Regulations 2026 (SL 2026/260)
Heritage New Zealand Pouhere Taonga Act 2014 (2014 No 26): section 107
"Related Legislation
"Related Legislation
"Related Legislation
Versions
Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
More
Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2009
RSS feed link copied, you can now paste this link into your feed reader.